Project Management

Amended due to COVID-19 pandemic, work resuming.
By June 2023, General Services will develop a capital project and tenant improvement system to track progress from inception of project to completion and reduce project delivery times by 5%.

Key Steps

1 2 3 4
Develop sample gant chart appropriate for capital projects and one for tenant improvements. Determine sample capital project and tenant improvement project to test gant chart effectiveness then modify as needed. Develop procedure for gant chart completion and share with facilities staff.  
Plan Reference:
Target:
Baseline: Progress:
6.C.i, 6.C.ii 190 Days 200 100% (190)
10 day reduction in construction days between projected completion and actual completion date.