# 290

Pajaro Flood Financing

By June 2022, Public Works (Zone 7), in collaboration with local and State partners, will pursue financing strategies for the Pajaro River Flood Risk Management Project.

Verification link/documentation

Key Steps

1 2 3 4
Assist State delegation in drafting legislation, in coordination with input from State Department of Water Resources and others. Negotiate legislation, and develop initial Subventions Agreement for local cost share of the project. Develop Engineer's Report, and conduct benefit assessment district formation process. Modify Subventions Agreement either inside of or outside of project implementation phasing, recognizing legislative outcome.
Plan Reference:
Target:
Progress:
1.B.ii,  4.C.ii, 4.D.i Local Cost Share Agreement 100%