Divert Organic Waste
By December 2022 June 2021, Public Works will fully implement organic waste diversion for all businesses and single-family homes in the County.
Verification link/documentation
Key Steps
1 |
2 |
3 |
4 |
Complete design for Buena Vista compost facility. |
Complete permitting for new facility and begin construction. |
Complete outreach to affected businesses and residents. |
Begin expanded collection. Send to Monterey waste management district until a new facility is completed. |
Plan Reference: |
Target:
|
Baseline: |
Progress: |
4.B.i |
44,569 Businesses and Homes |
0 |
100% (44,569) |
The State mandates organics waste diversion as part of a Greenhouse Gas Reduction requirement. It is estimated that approximately 20% of California’s methane gas emissions are generated from organic waste decomposing in the landfill.